Friday 13 December 2013

Valley Clubhouse Update - December 13, 2013

Retaining wall being formed on
South side
 
 Most of the Foundation Walls were poured this week for the clubhouse. They have to still pour Foundation Walls for retaining walls and the one end of the club house. This process has been much slower than anticipated. The weather this week definitely slowed the contractor down. Hopefully they will be able to make up some time before the real freeze! The goal next week is to pour the retaining wall foundations and start back filling before Christmas.   Until next time....  David






View from the North side

No comments:

Post a Comment